Halcyon Grid

Dispatch intelligence for the batteries already on the grid.

Series A €18M September 2026

Studio Helper — self-initiated concept
Halcyon Grid is a fictional company. No figure here is a real result.

Open on the curve, not the name. "Every battery on the grid makes the same decision a few thousand times a day: buy now, or sell now. Most of them get it wrong, because the software telling them was written once and never learned anything. We are the layer that decides." Do not read the subline aloud — it is on the slide.
Halcyon Grid 02

The problem

Batteries are asked to make a market decision with a thermostat.

Most installed storage runs on logic fixed at commissioning — a charge window, a price threshold, a schedule someone wrote once. Wholesale price moves every five minutes. The two are not the same problem.

66%

of US utility-scale battery capacity lists price arbitrage among its uses — but only 41% runs it as the primary strategy.

EIA, Sept 2025 · public domain

3.4M

MWh of wind and solar curtailed in CAISO in 2024, up 29% year on year. Solar was 93% of it. Clean power thrown away while storage sat idle.

EIA, May 2025 · public domain

6%

of all hours in 2025 cleared at negative prices in France, Germany, the Netherlands and Spain. In Spain the count doubled in a single year.

Ember, European Electricity Review 2026 · CC BY 4.0

The gap is not hardware and it is not capital. It is that the asset does not know what the next four hours are worth.

Three numbers, three sources, all citable. Do not editorialise the curtailment figure — let it sit. If asked whether curtailment is a transmission problem: partly, but a battery that charges during a curtailment event converts a constraint into inventory.
Halcyon Grid 03

Why now

The assets arrived before the intelligence.

US utility-scale battery capacity has grown at roughly 70% a year for three years, and another 54 GW is already in the pipeline. Globally, 108 GW was added in 2025 alone — 40% more than the year before.

An optimisation layer needs assets to sit on top of. Three years ago there were not enough to build a company on. There are now, and every one of them is commissioned with software that will never improve on its own.

EIA, Aug 2026 (public domain) · IEA, May 2026 (CC BY 4.0)

43.6 End 2025 operational 51.9 Mid 2026 +8.3 GW in H1 105.9 By 2028 announced pipeline GW · US UTILITY-SCALE BATTERY STORAGE

Dashed bar is announced pipeline, not installed capacity. Global storage could reach 1,200 GW by 2030 — but that figure is the IEA's Net Zero Emissions pathway, a normative scenario rather than a forecast, and is shown here only for scale.

The dashed bar matters: never present pipeline as installed. If a partner tests the 1,200 GW number, agree with them immediately — it is a policy scenario, which is exactly why it is in the caption and not on the chart.
Halcyon Grid 04

The insight

The largest battery
on the grid is the one
nobody built.

Every megawatt-hour of storage installed in the last five years is still there, still connected, and still being dispatched by whatever logic was loaded at commissioning. Most of it follows a fixed schedule or a single price threshold.

That installed base is larger than anything a new entrant could finance, and it is available today. Changing what an asset does requires no steel, no permit and no grid connection — only permission and an API.

We do not build batteries. We change the decisions the existing ones make.

This is the turn of the pitch. Pause after the headline. The objection you will get: "why hasn't the OEM done this?" — answer on the moat slide, don't pre-empt it here.
Halcyon Grid 05

What we do

A dispatch layer between the market and the asset.

Halcyon Grid sits between price and hardware. It forecasts, it decides, it instructs, and it measures what actually happened — then feeds that back.

Forecast price · weather grid constraint Optimise state of charge degradation cost Dispatch setpoints to the site controller Settle measured uplift against baseline EVERY DISPATCH BECOMES A LABELLED TRAINING EXAMPLE 5-min horizon mixed-integer solve Modbus / OCPP / API

No hardware. Nothing is installed on site. We speak the protocol the controller already speaks.

No capex for the owner. The asset is theirs; the uplift is shared.

Days, not quarters. Integration is a credential exchange and a shadow-mode period.

Land "no hardware" hard — it is the whole reason the gross margin story works. If asked about safety: we operate inside the owner's own limits, and shadow mode runs for two weeks before we touch a setpoint.
Halcyon Grid 06

One asset, one day

The decision, made 288 times a day.

Charge Discharge
-40 0 60 120 180 EUR/MWh 00:00 06:00 12:00 18:00 EUR -12 PAID TO ABSORB EUR 210 EVENING PEAK CHARGE · 20 MW DISCHARGE · 20 MW DISPATCH
€222
Spread across the day, per MWh
6
Hours charging, at or below zero
4
Hours discharging, into the peak

Modelled day on a real market shape. Not an observed trade.

Walk the chart left to right, once, slowly. The midday dip below zero is the moment the room understands the business: the asset is being PAID to absorb energy, and four hours later it sells the same energy into the peak. Do not explain the optimiser here; they are buying the shape of the trade.
Halcyon Grid 07

Market

Built from installed megawatts, not from a percentage of someone else's trillion.

43.6 GW

US utility-scale storage operational

EIA, end-2025

× 66%

lists arbitrage among its uses

EIA, Sept 2025

× €6k

platform fee per MW-year

Our pricing — illustrative

€173M

US platform revenue, addressable today

Recurring, before performance share

Europe, same arithmetic

The EU fleet passed 10 GW in 2025, more than double the 4 GW of 2023, with a pipeline above 40 GW. On the same attach rate and the same fee that is a further €40M of addressable platform revenue, growing faster than the US.

Ember, European Electricity Review 2026 · CC BY 4.0

Why the number grows on its own

The denominator is installed capacity, and it is compounding at roughly 70% a year in the US. We do not need to win share faster than the market to grow — though we intend to.

What we have deliberately excluded

Behind-the-meter and EV fleets, which are larger again and structurally similar. They are not in this figure. A market slide that counts everything is a market slide nobody believes.

Show the multiplication, left to right, and stop. The excluded-segments column is the credibility move — say out loud that behind-the-meter is not counted. If they push on the €6k fee, it is the one assumption here that is ours rather than published, and it is defensible against what asset managers already pay for far less.
Halcyon Grid 08

Business model

A contracted floor, and a share of what we add above it.

Line one · contracted

€6,000 per MW-year

Platform fee, billed monthly, three-year term. This is the only number we call ARR.

Line two · variable

30% of measured uplift

Against a counterfactual baseline agreed with the owner before we touch a setpoint. Reported separately, never blended into ARR.

Where a megawatt-hour of uplift goes

100 70 30

Gross uplift captured

To the asset owner

Halcyon Grid

The objection, and the answer

“Performance revenue is low quality.” Correct, if it is all you have. So the platform fee is contracted and covers gross margin on its own; the share is upside. Every customer also carries a floor and a cap, which makes the variable line forecastable within a band rather than a hope.

Pricing and split are illustrative — this company does not exist.

Lead with the floor, not the upside — investors discount outcome pricing hard and you want to pre-empt it. The 70/30 split is the number most likely to be negotiated in diligence; know your walk-away.
Halcyon Grid 09

Traction

Eight quarters, compounding.

Every figure on this slide is illustrative. Halcyon Grid is a concept company; these are modelled against published Series A benchmarks, not achieved results.

0 2 4 6 Q1 25 Q4 25 Q4 26 EUR M

ARR, contracted platform fee only — performance share excluded.

€6.2M
ARR, exiting Q4
3.4×
Year on year
128%
Net revenue retention
79%
Gross margin
11 mo
CAC payback
1.3×
Burn multiple

Benchmarks for context: Series A median ARR €2.5M, NRR 101%, gross margin 77%, CAC payback 15 months. Sources: CRV, Benchmarkit 2025.

Expansion is the story, not logo count — NRR of 128% says every megawatt we win brings more with it. Be ready to show the quarterly net-new ARR build; cumulative curves hide deceleration and partners know it.
Halcyon Grid 10

Moat

Every dispatch we make is a labelled example nobody else has.

01 · Data compounds

We do not observe the market, we act in it. Each instruction produces a measured outcome against a known counterfactual — the one training signal a data vendor cannot buy.

02 · Registration is slow

Operating in a wholesale market means registration, compliance and settlement integration per market. It takes quarters. We have spent them.

03 · The baseline stays with us

Performance is measured against a history we hold. Switching does not just mean re-integrating — it means losing the record that proves what the asset is worth.

04 · Density beats scale

Forecast accuracy improves per market, not per customer. The tenth asset in a market makes the other nine better — a local network effect a global competitor cannot shortcut.

Why not the battery OEM

They sell hardware and optimise for warranty exposure. Cycling the asset harder is a cost to them and a revenue to the owner.

Why not the trading desk

Their model requires owning or tolling the asset. Owners who want to keep the asset — most of them — are not served.

Why not in-house

A single owner sees one portfolio in one market. The forecast they can build is bounded by their own fleet.

The OEM answer is the strongest and the one they will test. Warranty incentive misalignment is real and checkable — offer to introduce them to an owner who has hit it.
Halcyon Grid 11

Go to market

One site proves it. The portfolio follows.

01

Land

A single site, free, in shadow mode. We produce the instructions we would have sent and report what they would have earned. Two weeks, no risk, no integration to undo.

Sales cycle 6–10 weeks

02

Expand

Shadow-mode evidence converts to the portfolio, because the owner now has a number for what the rest of the fleet is leaving behind. This is where the 128% retention comes from.

Median 4× MW at 12 months

03

Channel

Asset managers and independent power producers carry us into fleets we would never reach one site at a time. They keep the relationship; we keep the dispatch.

Two signed, four in diligence

The motion is deliberately bottom-up. Storage owners will not sign a control agreement on a slide deck — but they will let you watch, and the watching produces the evidence that closes them.

4.2×
Pipeline coverage against plan

Illustrative

Shadow mode is the whole GTM and it is genuinely differentiated — it removes the only real objection, which is trust in an outside system touching a live asset. Say that plainly.
Halcyon Grid 12

Team

Three disciplines that rarely sit in one room.

This deck is a concept, so no individuals are named or invented. What a real deck would carry here is the composition below and the reason this specific group is the one to back.

Grid operations

Someone who has been on the control-room side of a dispatch instruction and knows why an owner says no. Carries market registration and the relationships that shorten it.

Quantitative trading

Short-horizon forecasting and execution under uncertainty, from a desk where being wrong cost money. Owns the optimiser and the risk limits around it.

Production ML infrastructure

Models that run every five minutes against live assets, with rollback. This is a reliability problem before it is a machine-learning one.

14
Today
31
At 18 months, post-round
9
Of the next 17, in engineering

Headcount illustrative

In a real deck this slide is names, faces and one line each on why them. The composition argument still matters: grid + quant + infra in one room is genuinely rare, and it is the reason the product can exist.
Halcyon Grid 13

The ask

€18M

Series A · 24 months of runway to 2,000 MW under management

Lead sought · board seat offered
Existing investors participating pro rata

Use of funds

42% 21% 19% 12% 6%

Engineering & data science · €7.6M

Market operations & compliance · €3.8M

Commercial & partnerships · €3.4M

Infrastructure & security · €2.1M

Working capital · €1.1M

By month 6

Two further markets registered and live.

By month 12

1,000 MW under management. €12M ARR.

By month 18

Channel contributing a third of net new MW.

By month 24

2,000 MW. Series B on metrics, not narrative.

Round size, allocation and milestones are illustrative.

Name the milestone that unlocks the Series B and make it a metric, not a narrative. The allocation splits are the part diligence will model — be able to defend engineering at 42%.

A volatile grid,
made calm.

The batteries are already built. We decide what they do next.

Series A · €18M halcyongrid.example

Studio Helper — self-initiated concept · Halcyon Grid is a fictional company

Stop talking after "made calm". Let the silence do the work, then ask for the meeting.
← → navigate · O overview · F fullscreen
01 / 14